top of page
Search
The NZ Building Economist
Sep 15, 2023
Head Contractor WDR excludes Subcontractor Time-related Costs
It is time to dispel the myth some Principal representatives have asserted, in recent times, that the Head Contractor Working Day Rate...
0 comments
The NZ Building Economist
Mar 3, 2023
'Project Specific' Overhead Recovery
NZS3910 misrepresents Overheads as ON SITE, or OFF SITE... Our definitions are clear, but our terminology is misleading. The NZS3910...
0 comments
The NZ Building Economist
Oct 5, 2022
One Notice Will Do, for “Extension of Time Variations” NZS3910
Have you been awarded an extension of time for a variation but denied the money for the variation and its time related costs for lack of...
0 comments
The NZ Building Economist
Aug 28, 2022
The Universal Overhead and Profit Recovery Formula (For Head & Sub Contractors Equitable Recovery)
NZS3910:2013 does not prescribe how to calculate a Working Day Rate but it does guide you to include 'Time related costs', and as you...
1 comment
The NZ Building Economist
Apr 10, 2022
Getting to the Entitlement Point, is what really Matters
Qualifying circumstances must always be treated as a variation. It is a choice to argue badly as a tactic to distract, confuse, delay,...
0 comments
The NZ Building Economist
Nov 28, 2021
The Principles of Valuation NZS3910:2013
Here we explore [1] Valuing Variation, [2] Valuing Other Matters, and [3] the Principles of Valuation, to be applied to everything being...
0 comments
The NZ Building Economist
Nov 21, 2021
Subcontractor Extension of Time Dis-entitlement, No harm no foul
Three infill units, Auckland's North Shore 2021 There was a time when subcontractors were never allowed to be late. It was a time when,...
0 comments
The NZ Building Economist
Apr 21, 2021
Offsite Overhead Recovery Mission
Late one October 2020 evening, while discussing work war stories (dispute resolution) at a bar, a senior construction executive / QS...
0 comments
The NZ Building Economist
May 9, 2020
Time to break out a “Time related overheads” claim, NZS3910 Style.
The nature of a Covid-19 Shutdown causes extreme under recovery of Off-site Overheads using the standard Working Day Rate or % methods.
0 comments
The NZ Building Economist
Apr 4, 2020
Your Construction Contract [NZS3910] & the Covid-19 Shutdown
When it comes to Covid-19 the contract empowers the Engineer with the responsibility and power to suspend the contract works.
0 comments
bottom of page